Client: Taylor Woodrow Works involved demolishing slab concrete without piercing through the existing deck to allow new railway track to be laid lower than the existing track. Over 100 construction workers were employed, enabling the project to be completed over...
Bishop’s Place, Pedestrian Bridge, Herne St, Shoreditch Client: Vinci Construction The works involved the construction of a reinforced concrete wall and deck, with reinforced concrete columns in order to support a high level pedestrian walkway above Liverpool Street...
Client: Network Rail (Volker Fitzpatrick) The project consisted of the construction of concrete bases, heavy reinforcement and concrete works formed within the shuttered frame. Completed work handed over to clients on time and within the budget.
Client: Siemens Dyneema Ltd was contracted as a subcontractor working for Siemens on a project to improve the security systems at the perimeter of the plant. The duct routes cumulatively, an overall length in excess of 5 km were laid in shallow trenches with...